The wooden walkway across the south end of Lake Camelot isn't coming back. In January 2025, the Minnesota Department of Natural Resources turned down Plymouth's request to rebuild it. Two fishing-pier docks now stand roughly where it crossed the water. The rest of the renovation, which the city has slated for substantial completion on October 15, 2026, follows from that decision. It all points toward one goal: a single path around the lake that stays usable 12 months a year.
If you've walked this park off Cheshire Parkway and Chankahda Trail for years, the new layout may look like a set of separate upgrades. There's a castle playground, a new restroom building, new boardwalks, and new docks. Taken together, they rebuild the park around its loop trail.
The Ruling That Set the Plan
The south boardwalk is more than 20 years old. The DNR findings date it to 2002, and the city's information sheet says staff built it sometime between 2003 and 2004. By the time the city applied to replace it, it had deteriorated. The DNR's Findings of Fact on permit 2024-3389, dated January 29, 2025, explain the denial in plain terms. A paved trail around the southern end of the lake, built in 2018, already let people circle the water and watch wildlife along the way.
In the DNR's words, from the same findings:
"Replacement of the existing boardwalk is not necessary for local residents to connect with wildlife or to circumnavigate the lake."
The agency also weighed what rebuilding would do to the water itself. The application estimated an excavation 500 square feet in area and 3 feet deep at each abutment, about 55 cubic yards apiece, and the DNR noted that the final design could bring more impacts not yet known. Dock piers, the findings said, were the "minimum encroachment alternative."
The DNR also pointed to Plymouth's own plan. The Lake Camelot Park Master Plan, which the City Council adopted on November 26, 2024, already showed the south boardwalk removed and replaced with fishing-pier docks. The city's boardwalk information sheet gives the same reasoning in shorter form: the DNR considers the existing trail a suitable alternative with less impact on the public water.
How Two Boardwalks Became One Loop
The north crossing got a different answer. The city's information sheet says the north boardwalk is being replaced with a drivable boardwalk as part of Chankahda Trail Phase 3. It links the Chankahda Trail path to the trails inside the park. According to the sheet, preliminary talks with the DNR suggested this one meets the agency's criteria, because no other location would work and it sits as close to the shoreline as possible.
That's what makes the south decision workable. The south end keeps its 2018 paved trail, and the docks give people a place to stand at the water. The north end gets a crossing that can carry a vehicle. The east side gets a replacement for its small bridge. With those three pieces in place, the city says maintenance staff "will be able to plow a continuous loop around Lake Camelot during the winter."
The drivable deck explains the choice. A boardwalk built for foot traffic would leave a gap in the winter loop. One that a plow can cross closes the circle.
The construction log on the city's Park & Trail Projects page shows the sequence:
- November 2025: The old north boardwalk is removed and salvaged, starting November 11, weather permitting.
- January 13, 2026: Removal of the south boardwalk begins.
- February 4, 2026: Installation of the south docks begins while the south boardwalk removal continues.
- April 15, 2026: The contractor arrives on site and the Cheshire parking lot closes for construction of the four-season restroom.
- April 21, 2026: The north parking lot closes, and the city says it will stay closed through the end of construction.
- August 21, 2026: East boardwalk installation begins.
- September 3, 2026: The east boardwalk is built and its concrete approaches are poured. The trail between the north and east boardwalks has been reclaimed and is scheduled for paving.
Where Things Stood at the Last Update
The latest Lake Camelot entry on the city's project page is dated September 3, 2026. No later confirmation that the park has fully reopened turned up. Here's how each piece was described that day, set against the October 15 target.
| Element | Status as of Sept. 3, 2026 |
|---|---|
| Castle playground | Installation had begun with the castle, and a crane set the three tallest pieces. The full job, including poured-in-place surfacing, was expected to take another 4 to 6 weeks |
| Four-season restroom, Cheshire Parkway lot | Nearly finished, with final touches and inspection left. It opens to the public once the certificate of occupancy comes through |
| East boardwalk | Built, concrete approaches poured |
| Trail between north and east boardwalks | Reclaimed, paving scheduled that week, weather permitting |
| Paving at the restroom and both docks | Scheduled that week, weather permitting |
Count four to six weeks from early September and the playground timeline lands right around mid-October. That's consistent with the city's target, but nothing posted so far says the work is finished.
The playground is a bigger change than it might sound. The master plan splits it into a 1,800-square-foot area for ages 2 to 5 and a 4,600-square-foot area for ages 5 to 12. The plan keeps the existing shelter and adds the restroom, docks, an overlook, and trail connections.
The restroom's location is worth knowing. It sits at the Cheshire Parkway parking lot, 5724 Cheshire Parkway, which the city's updates also describe as the lot that serves the southwest trailhead. Because it's built as a four-season building, the plan has a working restroom at the loop's trailhead when the plowing starts.
The Chankahda Piece Is Still Open
There's one practical catch for the next few weeks. Plymouth is rebuilding Chankahda Trail this year from Cheshire Parkway to Northwest Boulevard, and new trails are part of that project. In the city's Chankahda Trail reconstruction update dated October 8, 2026, the road was still closed between Cheshire Parkway and Yucca Lane while crews worked on sewer, retaining walls, and grading. That segment is scheduled to reopen in November 2026.
The north boardwalk belongs to that same Phase 3 work, which makes the November reopening the date to watch. Until then, the Cheshire Parkway side is the clearer way in. In April the city said the north lot would stay closed through the end of construction.
The Same Idea at Plymouth's Other Parks This Fall
Lake Camelot isn't the only park where Plymouth is spending this fall on connecting trails rather than adding attractions.
- Plymouth Creek Trail. A 500-foot boardwalk and about a tenth of a mile of new asphalt trail will give the Plymouth Community Center an accessible off-street connection to the Hilde Performance Center, the Plymouth Ice Center, and City Hall. Lights, trail counters, and wayfinding signs are part of the plan. On September 3, the city said helical pile installation would wrap up the following week, with deck work next.
- Fall trail paving. Trails at Circle, Gleanloch, Green Tree Island, Harbor Lane, Lions, and Three Ponds parks are scheduled for paving this fall, along with Circle Park's basketball court. The city warns of temporary closures around the work zones.
- South Shore Park. The renovation brought a new playground, benches, signs, a relocated basketball court, replaced trail, a drinking fountain, and bike racks. As of the August 21 update, only two signs and a backordered ADA swing were left.
- Parkers Lake Park. Starting in late October, the forestry and horticulture teams will work on a grove of declining oaks west of the building. They plan to loosen compacted soil, bring in soil better suited to oaks, and add irrigation for future dry spells. The understory will go back to native oak savanna.
The Parkers Lake work lines up with the city's Halloween at the Lake on Friday, October 30, from 5 to 8 p.m. The event listing gives two addresses, Parkers Lake Park at 15205 County Road 6 and Parkers Lake Playfield at 15500 County Road 6, so check the listing before you head over. The event is free and includes inflatables, pumpkin bowling, bingo, LED mini golf, a sensory station, an interactive DJ, and a touch-a-truck lineup of police and fire vehicles. Costumes are encouraged, and you'll want cash or a card for the food trucks.
Back at Lake Camelot, the city's own plan sums up what the year of construction was for. With the drivable north boardwalk and the rebuilt east bridge in place, Plymouth intends to keep the full path around the lake open after the snow falls.
If the Lake Camelot loop is part of your week and you've wondered how a park like this one, or a trail project still underway, figures into what nearby homes are worth, we're happy to talk it through over coffee. At Avenues & Acres Home Team, we follow these northwest Plymouth projects as closely as we follow the market. Request your free concierge consultation and we'll walk you through what we're seeing.